Construction Updates

Monday, July 10th 5:30 a.m.

Construction of the Tunnel Influent Pump Station (TIPS) is underway at the Kailua Regional Wastewater Treatment Plant. On Monday, July 10th, the TIPS contractor will need to place the TIPS ground level slab, which will require construction truck deliveries prior to 8:30 a.m. due to the large quantity of concrete to be placed. During this timeframe, the TIPS contractor will minimize and control the use of back up alarms as much as possible.

A pump truck is scheduled to arrive onsite at 5:30 a.m. and the first concrete truck is scheduled to arrive at 6:00 a.m.  Deliveries will continue throughout the day until approximately 4:00 p.m.

If you have any questions or concerns, please feel free to contact the Construction Management Team via the 24-hour project hotline at (808) 445-9079 or email info@kktunnel.net.

 

Mahalo for your patience and understanding.