Construction Updates

Morning Cement Deliveries to Kaneohe Pre-Treatment Facility

Grouting of the 10-foot, 3-mile long sewer tunnel has commenced. In order to maximize the daily grout installation rate, additional quantities of cement are needed prior to the start of construction each day to replenish the quantity installed during the prior night shift. Based on the quantity of cement...

Tanker Trucking near Kaneohe Wastewater Pre-Treatment Facility

The delivery of the 10-foot inner diameter tunnel pipes to the Kaneohe Wastewater Pre-treatment Facility and installation within the tunnel is complete. Up next, the tunnel contractor will grout the pipes in place. To do so, they will need approximately 12-20 tanker loads of cement delivered daily (Monday –...

Night Work at Kailua Regional WWTP – 03/02/17 and 03/03/17

Aloha, This notice is to inform you that the Tunnel Influent Pump Station (TIPS) General Contractor will be working within the Kailua shaft tonight and tomorrow night. As a result, you may notice the tower crane in operation all through the night. Since it’s an electric crane, we do...

Kailua Regional WWTP – Odor Due to Electrical Issues – Power Restored

Aloha, At 8:40pm last night, power was fully restored at the Kailua Regional Wastewater Treatment Plant and all operations are back to normal.  If you have any questions or concerns, please feel free to contact the Construction Management Team via the 24-hour project hotline at (808) 445-9079 or email info@kktunnel.net....

Kailua Regional WWTP – Odor Due to Electrical Issues

Aloha, Due to a power outage within the Kailua Regional Wastewater Treatment Plant, some systems have been powered down as a precautionary measure until repairs can be made. As a result, you may notice an odor until power has been fully restored. Crews are currently on-site investigating the issue...

Oversize Vehicles near Kaneohe Wastewater Pretreatment Facility

Pipe installation in the approximately 3-mile long tunnel has commenced. As a result, oversize trucking operations will re-commence this week and are expected to continue through June 2017 between the hours of 8:30 a.m. to 6:00 p.m. The impacted area will begin at the intersection of Puohala Street and...

12/19/16 Night Work – Aikahi Loop

December 19th to 23rd – 10pm to 6am Night work is scheduled to commence on the evening of Monday, December 19, 2016*, at approximately 10:00pm on a section of Aikahi Loop near the Kailua Regional Wastewater Treatment Plant. The Tunnel Influent Pump Station General Contractor will be accessing a...

Public Informational Meeting – Thursday, December 1, 2016

Southland/Mole Joint Venture (SMJV) and the City and County of Honolulu invite you to a public informational meeting regarding the 24-hour noise variance granted for the construction of the intermediate shaft at the Board of Water Supply Kapa’a Water Tank site for the Kaneohe/Kailua Tunnel Project, City and City...

Additional Contractor Parking

Construction of the Tunnel Influent Pump Station (TIPS) and Headworks Facility is underway at the Kailua Regional Wastewater Treatment Plant. In order to accommodate the increase in crews at the KRWWTP required to perform this work, additional contractor parking is needed.  A review of open areas near the KRWWTP was...
Monthly Construction Photos